Woollahra Train Station Development


The NSW Government’s draft rezoning proposal for the Edgecliff–Woollahra precinct 

Allegra has made a submission to the Department of Planning, Housing and Infrastructure (you can read the submission here). Consistent with the position she has held since the proposal was announced, she supports more well-located housing near transport and the completion of the long-dormant Woollahra station, but her submission presses the Government on the detail — the evidence base for the dwelling numbers, whether the funding model and delivery assumptions stack up, infrastructure, heritage and character, affordable housing, and genuine consultation. A summary of her position is below.


What is proposed

On 24 August 2025 the NSW Government announced it would complete the partially built Woollahra train station (first started in the 1970s) and undertake a State-led rezoning of land around the new Woollahra station and the existing Edgecliff station.

On 8 September 2026 the Department released its detailed draft proposal (an Explanation of Intended Effect) for public exhibition. In summary, the proposal:

  • covers a 168-hectare precinct and would enable up to approximately 9,400 new homes (originally announced as up to 10,000) over roughly 20 years;
  • allows buildings of up to 34 storeys around Edgecliff station and up to 32 storeys around Woollahra station, with heights up to 121 metres on identified “Key Sites”;
  • concentrates growth around the stations, with around 40% of new homes within 200 metres of a station;
  • includes a 3% base affordable-housing contribution (rising to up to 15% on certain sites);
  • funds the station partly through “value capture” — a Transport Project Component of $15,000 per new dwelling (or $200 per square metre of new commercial floor space) within 800 metres of Woollahra station, plus uplift in land values;
  • proposes 7 new parks, around 9 kilometres of new walking and cycling connections, and about 1,000 new local jobs.
  • Once operational (targeted for 2029), the new station would connect to the Sydney CBD in about 8 minutes. The rezoning is expected to be finalised in 2027.

More detail, the webinar and a fly-through are available on the Department’s Edgecliff–Woollahra precinct page and on the Transport for NSW — Woollahra Station Activation page.


Woollahra Council’s alternative approach

On 12 August 2026, Woollahra Council released its own alternative approach for the precinct. Council’s plan accommodates up to 3,600 new dwellings — well below the Government’s figure — and is based on Council’s transport, economic-feasibility, social-infrastructure and urban-design studies.

Council argues its approach still delivers substantial housing growth while better protecting local infrastructure capacity, heritage (Council notes around 57% of the rezoning area sits within Heritage Conservation Areas), tree canopy, solar access and neighbourhood character. Council has also raised concerns about affordability, traffic, and the funding of the station and supporting infrastructure.

You can read Council’s alternative in full on its State-led rezoning page and in its news release.


Woollahra Council community information session (10 September 2026)

Council held a community information session at Woollahra Library at Double Bay on the rezoning and its alternative approach. If you missed it:


Where Allegra stands

Allegra supports building more homes close to public transport, jobs and services, and has said that areas like Woollahra and Edgecliff must play their part in addressing the housing shortage. She welcomes the completion of the Woollahra station.

Allegra has previously written to Planning and Public Spaces and met with Transport for NSW to press the Government on how the proposal is delivered. 

On 21 September 2026 Allegra wrote to the NSW Premier, the Hon. Chris Minns, to request a longer exhibition and submission period (which was granted and extended to 30 October 2026); and to request a formal and substantive response to the alternative strategy put forward by Woollahra Council. Given the scale of the development, the NSW Government should explain clearly where and why its approach differs to the Council.


Allegra's Submission

You can read Allegra's submission to NSW Planning here


Results of our Survey

You can see the results of our community Survey on this issue here


Next Steps

Allegra will keep the community updated as the rezoning progresses.

This page is for information only. Details, dates and links are current as at the drafting date above and are subject to change by the NSW Government and Woollahra Council — please check the linked pages for the latest information.